PUBLIC NOTICE: Crystal Lake Excavation Point Roadway Project

(May 6, 2024 | 9:50am)

Excavation Point, Inc. (EPI) will be in Crystal Lake starting Thursday, May 9th, 2024 to perform asphalt work.

The schedule below is tentative:

 

Tentative Schedule

  • Milling
    1. Snead Circle – May 9th
    2. South Flamingo Rd: S. Country Club Dr. to E. Crystal Lake Dr. – May 9th and 10th
    3. South Country Club Dr: From S. Flamingo Rd. to E. Crystal Lake Dr. – May 13th and 14th
  • Paving
    1. South Flamingo Rd: S. Country Club Dr. to E. Crystal Lake Dr. – May15th and 16th
    2. Snead Circle – May 17th
    3. South Country Club Dr: From S. Flamingo Rd. to E. Crystal Lake Dr. – May 18th and 19th

 

 

Any adjustment of days will move dates downward and will follow the same number sequence. If you have any questions, please feel free to contact the Public Works Office or the Public Works Director.