Parking Lot - 18 E Pine

Task                                                   Status  Date                                 Notes                                                                                                                                     
Proposal Received                           Completed          March 11, 2026               Proposal submitted by Polston Engineering for design and permitting services       
Proposal Approval Completed March 13, 2026 Approved to move forward per City Manager direction
Agreement Execution Completed March 2026 Proposal signed and authorized to proceed
Project Design Phase In Progress March 2026 – Present Engineering design and permitting plans currently underway
Land Clearing Pending April 2026 City staff will clear land in preparation for a future parking lot
Survey and Supporting Services Pending TBD Additional survey work and certifications may be required as design progresses
Permitting Pending TBD Will be submitted following completion of design plans
Construction Pending TBD Will begin after permitting approvals are secured