Task Status Date Notes
Project Planning & Concept Development In Progress Q1 2026 Finalizing design intent (dock, retaining wall, beach interface)
Survey & Site Assessment Pending Q2 2026 Includes shoreline conditions, elevations, and existing structures
Engineering Design (Dock & Retaining Wall) Pending Q2–Q3 2026 Structural design for seawall and dock layout
Funding & Budget Confirmation Pending Q2–Q3 2026 Align with CRA/CIP or grant opportunities
Construction Procurement (Bidding / Contractor Selection) Pending Q4 2026 Dependent on finalized plans and funding approval
Pre-Construction Meeting & Mobilization Pending Q4 2026 Contracts executed, permits issued
Construction Phase Pending Q1–Q2 2027 Seawall installation, dock construction, sand placement
Project Completion & Final Inspection Pending Q2 2027 Final approvals and project closeout