| Task | Status | Date | Notes |
| Project Planning & Concept Development | In Progress | Q1 2026 | Finalizing design intent (dock, retaining wall, beach interface) |
| Survey & Site Assessment | Pending | Q2 2026 | Includes shoreline conditions, elevations, and existing structures |
| Engineering Design (Dock & Retaining Wall) | Pending | Q2–Q3 2026 | Structural design for seawall and dock layout |
| Funding & Budget Confirmation | Pending | Q2–Q3 2026 | Align with CRA/CIP or grant opportunities |
| Construction Procurement (Bidding / Contractor Selection) | Pending | Q4 2026 | Dependent on finalized plans and funding approval |
| Pre-Construction Meeting & Mobilization | Pending | Q4 2026 | Contracts executed, permits issued |
| Construction Phase | Pending | Q1–Q2 2027 | Seawall installation, dock construction, sand placement |
| Project Completion & Final Inspection | Pending | Q2 2027 | Final approvals and project closeout |