| Task | Status | Date | Notes |
| Project Initiation & Coordination with FDOT | Completed | Jan 2026 | Project initiated in coordination with FDOT and City |
| Traffic Study Submission to FDOT | Completed | Mar 5, 2026 | Study submitted and used to support design phase |
| Field Data Collection | Completed | Mar 2026 | All field work completed and delivered to engineer |
| Preliminary Roadway Design | In Progress | Mar 2026 – Present |
Design phase underway; preliminary plans in progress |
| Natural Resource Assessment (Environmental Review) | Completed | Mar 2026 | Protected species and plants identified within project area |
| Additional Environmental Surveys (FDOT Requirement) | In Progress / Ongoing | Mar–Oct 2026 | Seasonal surveys underway as required for permitting |
| Environmental Survey Coordination | In Progress | Mar–Oct 2026 | Surveys coordinated to align with regulatory timeframes |
| Permitting Coordination (FDOT & Regulatory) | Pending | TBD | Will proceed alongside and following environmental clearance |
| CCNA Certification (City Attorney Signature) | Completed | April 2026 | Certification completed for FDOT extension submission |
| Final Design Completion | Pending | TBD | Dependent on environmental clearance and permitting |
| Construction Timeline Determination | Pending | TBD | To be determined based on FDOT approvals and final design |
| Estimated Project Completion | Revised | June 2027 (Anticipated) | Reflects pending PTGA extension approval |