State Road 64

Task Status Date Notes
Project Initiation & Coordination with FDOT Completed Jan 2026 Project initiated in coordination with FDOT and City
Traffic Study Submission to FDOT Completed Mar 5, 2026 Study submitted and used to support design phase
Field Data Collection Completed Mar 2026 All field work completed and delivered to engineer
Preliminary Roadway Design In Progress Mar 2026 – Present

Design phase underway; preliminary plans in progress

Natural Resource Assessment (Environmental Review) Completed Mar 2026 Protected species and plants identified within project area
Additional Environmental Surveys (FDOT Requirement) In Progress / Ongoing Mar–Oct 2026 Seasonal surveys underway as required for permitting
Environmental Survey Coordination In Progress Mar–Oct 2026 Surveys coordinated to align with regulatory timeframes
Permitting Coordination (FDOT & Regulatory) Pending  TBD Will proceed alongside and following environmental clearance
CCNA Certification (City Attorney Signature) Completed April 2026 Certification completed for FDOT extension submission
Final Design Completion Pending TBD Dependent on environmental clearance and permitting
Construction Timeline Determination Pending TBD To be determined based on FDOT approvals and final design
Estimated Project Completion Revised June 2027 (Anticipated) Reflects pending PTGA extension approval