MLK Sports Complex

Task Status Date Notes
Parking Lot Resurfacing

Completed 

Mar 2026

Work has been completed
Basketball Court Resurfacing

Completed

Mar 2026

Court improvements finalized
Turf Removal

Completed

Mar 2026

Existing turf removed
Grade Adjustment

Completed

Mar 2026

Will begin following turf removal completion
Irrigation Installation

Completed

Mar 2026

Installation to follow grading work
Turf Installation

Completed

April 2026

New turf installation
Press Box Upgrade (Audio & A/C)

Procurement Phase

Pending

Includes audio equipment and air conditioning unit improvements. Paint work almost complete
Estimated Project Completion

Pending

July 2026

Subject to construction progress and weather conditions