| Task | Status | Date | Notes |
| Parking Lot Resurfacing |
Completed |
Mar 2026 |
Work has been completed |
| Basketball Court Resurfacing |
Completed |
Mar 2026 |
Court improvements finalized |
| Turf Removal |
Completed |
Mar 2026 |
Existing turf removed |
| Grade Adjustment |
Completed |
Mar 2026 |
Will begin following turf removal completion |
| Irrigation Installation |
Completed |
Mar 2026 |
Installation to follow grading work |
| Turf Installation |
Completed |
April 2026 |
New turf installation |
| Press Box Upgrade (Audio & A/C) |
Procurement Phase |
Pending |
Includes audio equipment and air conditioning unit improvements. Paint work almost complete |
| Estimated Project Completion |
Pending |
July 2026 |
Subject to construction progress and weather conditions |