Central Ave

Task Status Date Notes
Project Planning & Design Development Completed Q1 2026 Drawings completed and ready for next phase
Contractor Site Visit Coordination Pending – Next Step Immediate Site walk needed with potential contractors
Construction Cost Validation / Quotes Pending Q2 2026 Pricing confirmed following site visits
Funding & Budget Confirmation Pending Q2 2026 Final costs will inform funding allocation
City Council Approval (AIS Submission) Pending Q2–Q3 2026 Required for project authorization and funding approval
Agreement / Contract Execution Pending Q2–Q3 2026 Contract finalized with selected contractor (insurance + docs required)
Pre-Construction Meeting & Mobilization Pending Q3 2026 Notice to Proceed issued after full execution
Construction Phase Pending Q3–Q4 2026 Implementation of project improvements
Project Completion & Final Inspection Pending Q4 2026 Final walkthrough and closeout