City Entry Gateway Signs

Task Status Date Notes
Notice to Proceed Issued Mar 2026  
Permitting Coordination Initiated Complete Apr 2026 Electrical and plumbing permits through Highlands County; zoning verification required
Permits Issued Complete Apr 2026 Dependent on county and agency approvals
Site Work Commencement Complete Apr 2026 Clearing, grading, and utility relocation to begin upon permit approval
Pre-Completion Phase Complete May 2026 Both gateway signs installed
Project Completion   June 2026 Irrigation and Landscaping